Azelio’s introduction to the US market continues with the signing of an MoU with system integrator Trimark. With its expertise in power system controls Trimark will integrate Azelio’s long-duration storage into energy projects. Azelio’s storage solution can be coupled with PV, wind, or any other energy source to cost-effictively supply renewable power 24/7. The first projects are targeting 150 kW in 2021, followed by 3 MW in 2022, 6 MW in 2023, 12 MW in 2024, and 24 MW in 2025.
Trimark is based in California, US, and offers a fully integrated portfolio of services, ranging from hardware and software products to field installation, integration, testing, and ongoing maintenance of power plants. The company is contributing to ‘greening the grid’, supporting the reduction of greenhouse gas emissions. The aim of the collaboration with Azelio is to position Trimark as one of Azelio’s regional partners for the integration of Azelio’s long-duration storage in renewable energy projects within North America.